Workaround for showing subtasks?
b.lewer says:
Multiple subtasks that are due in the same week as the parent task don't show up individually in This Week view, which could be a dealbreaker on using RTM for me.
Does anyone have a workaround so that I could see those subtasks individually on my This Week list (or an equivalent SmartList)?
Would omitting a due date for the task, and creating a subtask called "Complete full task" with the task due date work? Or is there another route that I'm missing?
Does anyone have a workaround so that I could see those subtasks individually on my This Week list (or an equivalent SmartList)?
Would omitting a due date for the task, and creating a subtask called "Complete full task" with the task due date work? Or is there another route that I'm missing?
andrewski (Remember The Milk) says:
Hi b.lewer,
Thanks for your feedback. I've passed that around the rest of the team.
Omitting a due date in the parent task would work, or (at least specific to This Week) leaving the due date more than a week from now too.
Hope this helps a bit!
Thanks for your feedback. I've passed that around the rest of the team.
Omitting a due date in the parent task would work, or (at least specific to This Week) leaving the due date more than a week from now too.
Hope this helps a bit!