Viewing incomplete tasks from last week
rtm_user_123 says:
As part of my weekly review, I would like to see tasks from last one week that are still incomplete, so I can plan for next steps on these (defer, delete or schedule for later date).
A Smart search like dueBefore:today and dueAfter:" today - 7" will do the trick. Of course, the problem is dueAfter:" today - 7" will not work.
I could hard code the date from 7 days ago, such as: dueBefore:today and dueAfter:" 17 Jan" (17 Jan is the date one week before today). That will give me what I am looking for.
But it's ugly and requires me to change the date each week before I run the Smart search.
Any suggestions ?
Thanks !!
A Smart search like dueBefore:today and dueAfter:" today - 7" will do the trick. Of course, the problem is dueAfter:" today - 7" will not work.
I could hard code the date from 7 days ago, such as: dueBefore:today and dueAfter:" 17 Jan" (17 Jan is the date one week before today). That will give me what I am looking for.
But it's ugly and requires me to change the date each week before I run the Smart search.
Any suggestions ?
Thanks !!
andrewski (Remember The Milk) says:
Hi rtm_user_123,
It's not currently possible to use a past time period for a Smart List, sorry. It would be possible as you mentioned to hardcode it.
Let us know if we can help with anything else in the meantime!
It's not currently possible to use a past time period for a Smart List, sorry. It would be possible as you mentioned to hardcode it.
Let us know if we can help with anything else in the meantime!